MCQ Practice Mathematics 📖 A, B and C can complete a pice of work in 24, 6 and 12 days respectively. Working together, they will be complete the same wo... Favorite Practice Add to Book Explanation & Answer Detailed explanations and answers are restricted. Unlock full access by logging in to your account. 🔒 Unlock the detailed explanation and answers Log In / Sign Up PreviousA and B together can paint a wall in 3 days. A can do it alone in 5 days. How many days would it take B to do this job alone? NextA, B and C started a job which they can complete in 2 days. B can do the job in 5 days and C can do it in 4 days. After worki...